underground resources of quartz deposit, chamber system of development followed by the collapsing the pillars, pillars extraction, temporary sill pillar, level pillar, cancellation of worked out space, technical and economic comparison

Abstract

For extraction of underground reserves of interjacent zone (sublevel 366 / 346 m) a variant of room-and-pillar mining system has been used, it has a large amount of operational losses. IM of UB of RAS has developed a technical project with main technical solutions for excavating the reserves of vein № 175 on the level 346/316 m by chamber system of exploitation followed
by the collapse of pillars, which allows to reduce significantly the balance reserve loss of high-value quartz in subsoil. The main principles of the project and technical solutions for geotechnical and geomechanical justification of safe and efficient development of reserves on sublevel 346/324 m are shown. Based on current miningtechnical and geomechanical conditions,
a procedure for phased exploitation of pillar reserves and cancellation of worked out space on sublevel 346/324 m is recommended. The variants of pillars excavation and schemes of cancellation of worked out space have been examined and their technical and economic comparison has been conducted.