GROUNDING THE EXPEDIENCY AND STAGES OF RECULTIVATION THE «EASTERN» OPEN PIT OF THE MAGNITNAYA MOUNTAIN USING WASTES OF METALLURGICAL PRODUCTION

Authors

  • Ivan Pytalev the «Magnitogorsk State Technical University named after G.I. Nosov»
  • Nadezhda Khomenko f the Institute of metallurgy, machine building and material-graphics of the FSEI HPE «Magnitogorsk State Technical University named after G.I. Nosov»
  • Diana Kozlovskaya FSEI HPE «Magnitogorsk State Technical University named after G.I. Nosov»
  • Ilona Gaponova FSEI HPE «Magnitogorsk State Technical University named after G.I. Nosov»
  • Natalya Kuznetsova FSEI HPE «Magnitogorsk State Technical University named after G.I. Nosov»

Keywords:

open pit, dump, wastes of metallurgical productionwastes of metallurgical production, railway transport, dump car

Abstract

The article considers two variants of arrangement freight
delivery of slags in the «Eastern» open pit using railway
transport. It is proposed to use railway dumping in the
technical stage of reclamation. The calculation of economic indices of the «Eastern» open pit reclamation is
performed. The use of railway transport, to reduce
transport costs, contributes to the achievement of maximum economic effect from the use of the worked out pit’s
area and dumps of overburden rocks, formed as a container for disposal of industrial pit’s wastes and dumps for
placement metallurgical production wastes.

Published

2014-06-30

Issue

Section

GEOTECHNOLOGY, GEOECOLOGY, GEOECONOMICS